Thornden Park Rose Garden Paver Restoration/Accessibility Improvements

  • Project typeThornden Park Rose Garden Paver Restoration/Accessibility Improvements
  • Project value+/- $250,000 - $350,000
  • Contractor nameAppel Osborne Landscape Architecture
Thornden-Rose-Garden-Aerial

Project Location: Thornden Park E.M. Mills Rose Garden Paver Restoration & Accessibility Improvements

Project scope: The project includes a restoration project aimed at replacing approximately 10,000 square feet of brick paver pathways and increasing ADA access for individuals and groups throughout the garden. Over the years, these pathways have experienced wear and tear, leading to heaving, removal, and obstructions. The project seeks to restore these pathways ensuring a near-level and unobstructed circulation system within and around the garden, and through the central Gazebo. 

Funding Source: Parks Capital Improvement Funds

Project Timeline: The timeline is subject to change due to contractor schedules, material availability and weather.

  • Design Phase
    Start Date: Winter 2023
    Completion Date: April 2024
  • Procurement Phase
    Start Date: April 2024
  • Construction Phase
    Projected Start Date: Fall 2024 - Spring 2025
    Projected Completion Date: Spring 2025