Project Funding and Phasing
· Transportation Improvement Project
· 80% federal funding/20% City funding
· C&S Engineers—Engineer for Preliminary and Detailed Design - $2 mill budget approx.
· Construction in 2 Phases:
¨ Phase 3.1 - Colvin St. to Ballantyne Rd.
¨ $ 2.6 mill. estimated construction
¨ Estimated Construction start 2027
¨ Phase 3.2 - Ballantyne Rd. to Dorwin Ave.
¨ $ 10.2 mill. estimated construction
¨ Estimated Construction start 2029
¨ Will also replace two pedestrian bridges