Creekwalk Extension Project Phase 3

  • Project typeDesign Phase 3
  • Project valueOver $2 million for Design
  • Project scheduleWinter 2025 to Spring 2030
  • Contractor nameC&S Engineers - Design

The Creekwalk Improvement Project Phase 3 will extend the Creekwalk by adding 3 miles of trail along Onondaga Creek from West Colvin Street to Dorwin Avenue. Once completed, the full Creekwalk will span nearly 8 miles, connecting Onondaga Lake to Dorwin Avenue. This extension will provide a vital recreational corridor along the southern half of Syracuse, while also serving as an important commuter route for pedestrians and cyclists. Additionally, new access points to Onondaga Creek will be developed as part of the Creekwalk project. The project is currently in design phase and will include public meetings and feedback from residents starting in May 2025.

Download and View the Map(PDF, 3MB)

 

Project Goals

Project Goals

  • Provide recreation opportunities and creek access as recommended by the Onondaga Creek Revitalization Plan
  • Extend the Creekwalk Trail 3 miles though Southside and Valley (Total 8 trail miles from Onondaga Lake)
  • Create safe off-road walking and biking opportunities; Provide a commuter route through city
  • Improve access to Onondaga Creek for fishing, kayaking and canoeing
  • Replace pedestrian bridges at Van Duyn and Clary/Chaffee

 

 

 

 

 

What's Been Done

What Has Been Done So Far on the Project?

· Currently in design phase

· Public Outreach 2025 -

  •  Project flyers mailed to 6,000 residences along corridor
  •  Door-to-Door Outreach to 600 homes
  • City Webpage
  • Conceptual Project Route provided for public review and comment
  • Public Meetings in spring to fall 2025
  • Stakeholder Outreach
  • First round of public input on conceptual plan through meetings, webpage and email

 

 

 

Conceptual Trail Map

Conceptual Routing Map

 Creekwalk Phase 3 Map(PDF, 3MB)

Project Slideshow from Sept 2025 Meeting

Project Slideshow from Sept 2025 Meeting 

Syracuse-Creekwalk-Phase-III Slideshow(PDF, 3MB)

Creekwalk 3—Next Steps

Creekwalk 3—Next Steps

· Survey creek corridor (Colvin St. to Dorwin Ave.)

· Conduct cultural and environmental investigations/assessments

· Identify right-of-way needed for the trail (95% is already city-owned); no people displaced or homes to be taken

· Develop Preferred Route Alternative based on public input, feasibility and  budget

· Public Outreach on Preferred Alternative—project meetings,  TNT meetings, webpage, Community Advisory Group

· Prepare design report and seek design approval from NYSDOT

 

 

 

 

Project Funding and Phasing

Project Funding and Phasing

· Transportation Improvement Project

· 80% federal funding/20% City funding

· C&S Engineers—Engineer for Preliminary and Detailed Design -  $2 mill budget approx.

· Construction in 2 Phases:

¨ Phase 3.1 - Colvin St. to Ballantyne Rd.

¨ $ 2.6 mill. estimated construction

¨ Estimated Construction start 2027

¨ Phase 3.2 - Ballantyne Rd. to Dorwin Ave.

¨ $ 10.2 mill. estimated construction

¨ Estimated Construction start 2029

¨ Will also replace two pedestrian bridges

 

 

 

 

 

Project Timeline


Preliminary Design

Conceptual Route Outreach | January 2025

  • Conceptual Routing
  • Public Outreach & Input
  • Stakeholder Outreach

Preferred Alternative | Fall 2025

  • Develop Preferred Alternative
  • Public Outreach & Input
  • Field Survey
  • Environment/Cultural Investigations
  • Identify Right-of-Way (ROW) needed
  • Prepare Design Report
  • NYSDOT Design Approval

Detailed Design

Detailed Design | July 2026

  • Start detailed design of trail, vegetation, amenities, bridges
  • ROW purchase
  • Federal/State funding agreements
  • Common Council construction approval
  • Public Outreach
  • Complete final plans
  • NYSDOT approval to advertise

Project Letting

Project Letting | Winter 2026/27

  • Advertise project
  • Public bid on project
  • DBE and workforce goals
  • Construction contract
  • Public Updates

Phase 3.1 Construction

Phase 3.1 Construction Estimated Start - Spring 2027

  • Colvin St. to Ballantyne Rd. trail construction
  • Convert Onondaga Creek Blvd. to trail
  • Secure Phase 3.2 funding
  • Public Updates

Phase 3.2 Construction

Phase 3.2 Construction Estimated Start- Spring 2029

  • Ballantyne Rd. to Dorwin Ave. trail construction
  • Replace 2 pedestrian bridges
  • Creek access improvements
  • Public Updates

Project Complete | Estimated Fall 2030