Ritter & Paratore Contracting Inc. have a contracted agreement with the City to oversee the demolition of the 660,000 square foot structure and several ancillary buildings on the premises. They initiated site mobilization on Monday, April 15, 2024, erecting project fencing and installing soil erosion and sediment control measures. The demolition of the buildings is slated to commence in May, unfolding in phases with an anticipated completion by year's end. C&S Companies, in collaboration with their subconsultant Artic Enterprises, Inc., will conduct air quality monitoring throughout the demolition process to ensure the safety of the site and its neighboring communities. Following the demolition, site restoration will ensue, with a projected completion date set for the beginning of 2025.