Q: How long does the application process take?
A: The typical approval process from intake to approval typically takes between 9 to 14 weeks.
- Intake Consultation: Typically within one to two weeks after interest form submission.
- Walkthrough Report & Full Application Link: Typically within four to six weeks after home walkthrough.
- Completeness & Eligibility Review of Formal Application: Typically within four to six weeks after application submission.
These are general program timeframes rather than guarantees, and awards remain subject to complete documentation, eligibility, review, available funding, and application volume.
Q: What happens during the property walkthrough?
A: Program staff inspect the property, including the roof and mechanical systems. Staff also take photographs of interior and exterior areas to document pre-construction conditions. The photographs are used for the property assessment report and maintained in the applicant's file. The walkthrough typically takes approximately 20-30 minutes.
Q: How are applications prioritized?
A: Applications are accepted and reviewed on a rolling basis, subject to funding availability. Complete applications are reviewed and awarded on a first-come, first-served basis, with approval also considering eligibility, funding availability, and alignment with program goals.
Q: Can I begin work before receiving approval?
A: Applicants should not begin work until all program paperwork is finalized and SHSC has issued authorization to proceed. Expenses incurred before execution of the program agreement are generally ineligible unless specifically authorized under the program's cost-share rules or another written exception.
Q: How long to I have to complete the project?
A: Projects must generally be completed within nine months of the notice-to-proceed date, unless SHSC establishes a different period in your formal notice. Extensions are subject to review and approval and must be requested before the completion date, with an explanation and revised schedule.
Q: Can I change my project after it has been approved?
A: Any material, financial, or other change to an authorized scope of work must be approved by SHSC before the changed work is performed. An online Change Order Request Form must be submitted and approved in advance for the work to remain eligible for reimbursement. Additional costs are first drawn from the project contingency and may be shared by the owner and SHSC at SHSC's discretion.